Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, December 31 – Friday, January 6, 2017
(No work is scheduled for Saturday, December 31 or Monday, January 2, 2017)

All work subject to change (weather permitting)

  • Continue Phase 3 (of 3) west-side/SB roadway related construction b/t A St. & Dix St. incl. LID footers and underdrain pipe and utility work including stormdrain inlets and pipe and streetlight/traffic signal conduit, foundation and pole installations;
  • Continue sidewalk reconstruction along the w. side of Minn. Ave. b/t A St. & Dix St.;
    • During sidewalk construction, pedestrians will be diverted to temporary protected walkways in the new roadway (on the same side of the street).
  • Work on the Minn. Ave. Bridge over East Capitol St. is expected to resume during this period to include west side sidewalk widening and wheelchair ramp construction.

> December 24: Project Photos

> December 24: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, December 24 – Friday, December 30, 2016
(No work is scheduled for Saturday, December 24 or Monday, December 26, 2016)

All work subject to change (weather permitting)

  • Continue Phase 3 (of 3) west-side/SB roadway related construction b/t A St. & Dix St. incl. LID footers and underdrain pipe and utility work including stormdrain inlets and pipe and streetlight/traffic signal conduit, foundation and pole installations;
  • Continue sidewalk reconstruction along the w. side of Minn. Ave. b/t A St. & Dix St.;
    • During sidewalk construction, pedestrians will be diverted to temporary protected walkways in the new roadway (on the same side of the street).
  •  Work on the Minn. Ave. Bridge over East Capitol St. is expected to resume during this period to include west side sidewalk widening and wheelchair ramp construction.

> December 17: Project Photos

 

 

> December 17: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, December 17 – Friday, December 23, 2016
(No work is scheduled for Saturday, December 17, 2016)

All work subject to change (weather permitting)

  • Continue Phase 3 (of 3) west-side/SB roadway related construction b/t A St. & Dix St. incl. LID footers and underdrain pipe and utility work including stormdrain inlets and pipe and streetlight/traffic signal conduit and foundations;
  •  Continue sidewalk reconstruction along the w. side of Minn. Ave. b/t A St. & Dix St.;
    • During sidewalk construction, pedestrians will be diverted to temporary protected walkways in the new roadway (on the same side of the street).
  • Work on the Minn. Ave. Bridge over East Capitol St. is expected to resume during this period to include west side sidewalk widening and wheelchair ramp construction.

> December 10: Project Photos

> December 10: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, December 10 – Friday, December 16, 2016
(Light work is scheduled for Saturday, December 10, 2016)

All work subject to change (weather permitting)

  • Continue Phase 3 (of 3) west-side/SB roadway related construction b/t A St. & Dix St. incl. LID footers and underdrain pipe, curb/gutter and utility work including stormdrain inlets and pipe and streetlight/traffic signal conduit and foundations;
  •  Continue sidewalk reconstruction along the w. side of Minn. Ave. b/t A St. & Dix St.;
    • During sidewalk construction, pedestrians will be diverted to temporary protected walkways in the new roadway (on the same side of the street).
  • Work on the Minn. Ave. Bridge over East Capitol St. west side sidewalk widening was temporarily put on hold last week in order to review the existing bridge conditions and to redesign the wheelchair/bicycle ramps for improved safety

> December 3: Project Photos

> December 3: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, December 3 – Friday, December 9, 2016
(Work is scheduled for Saturday, December 3, 2016)

All work subject to change (weather permitting)

  • Continue Phase 3 (of 3) west-side/SB roadway related construction b/t Ridge Rd. & Dix St. incl. LID footers and underdrain pipe, curb/gutter, wheelchair ramps, utility work including stormdrain inlets and pipe and streetlight/traffic signal conduit and foundations;
  • Continue construction of realigned E. Cap. St. S. Serv. Rd. (Ridge Rd. extension);
    • EB Traffic will remain on the newly installed pavement section (permanent configuration) to face WB Ridge Rd. in order to complete the remaining section.
  • Continue sidewalk reconstruction along the w. side of Minn. Ave. b/t Ames St. & Blaine St.;
    • During sidewalk construction, pedestrians will be diverted to temporary protected walkways in the new roadway (on the same side of the street).
  • Continue work on Minn. Ave. Bridge over East Capitol St. including sidewalk demolition and construction of new/wider sidewalk