> February 25: Project Photos

> February 25: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, February 25 – Friday, March 3, 2017
(Work is scheduled on Saturday, February 25th, 2017)

All work subject to change (weather permitting)

  • Complete west-side sidewalk reconstruction at the SW corner of the bridge;
  • Continue east-side bridge sidewalk widening construction;
    • During this work pedestrians wishing to cross bridge at the east side will be diverted to the west side of Minn. Ave from Ames St. and to the south side of Ridge Rd. from Anacostia Rd.
  • Continue east-side sidewalk reconstruction b/t Dix St. & Ames St.;
    • During sidewalk reconstruction, pedestrians will be diverted to temporary protected walkways in the roadway (on same side of street).
  • ontinue east-side bioretention cell/LID structure footing installations b/t Blaine St. & A St.;
  • Continue east-side reconstruction of property walls b/t Blaine St. & Clay Pl.;
  • Continue east-side low coping wall construction (back of sidewalk areas) b/t Blaine St. & Clay Pl.;
  • Begin relocation of Comcast OH comm. line from old to new Pepco poles;
    • This work will begin Saturday, February 25th, 2017 and occur during evening night hours.

> February 18: Project Photos

> February 18: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, February 18 – Friday, February 24, 2017
(Work is scheduled over the President’s Day weekend including Saturday, February 18th and Monday February 20th, 2017)

All work subject to change (weather permitting)

  • Complete west-side sidewalk reconstruction at the SW corner of the bridge;
  • Continue east-side sidewalk reconstruction b/t Benning Rd. & Blaine St.;
    • During sidewalk reconstruction, pedestrians will be diverted to temporary protected walkways in the roadway (on same side of street).
  • Continue east-side bioretention cell/LID structure footing installations b/t Clay Pl. & Ames St.;
  • Continue east-side reconstruction of property walls b/t Blaine St. & Clay Pl.;
  • Begin east-side bridge sidewalk widening construction;
    • During this work pedestrians wishing to cross bridge at the east side will be diverted to the west side of Minn. Ave from Ames St. and to the south side of Ridge Rd. from Anacostia Rd.
  • Begin east-side low coping wall construction (back of sidewalk areas) b/t Blaine St. & Clay Pl.;
  • Begin relocation of Comcast OH comm. line from old to new Pepco poles;
    • This work will be performed during evening night hours.

> February 11: Project Photos

> February 11: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, February 11 – Friday, February 17, 2017
(Work is scheduled for Saturday, February 11, 2017)

All work subject to change (weather permitting)

  • Begin relocation of Comcast OH comm. line from old to new Pepco poles;
  • Abandon old fire hydrant at the NW corner of Minn. Ave. & A St.;
  • Continue west-side low coping wall construction (back of sidewalk areas) b/t Blaine St. & Dix St;
  • Open west-side (southbound) Ames St. bus stop which has been relocated to south of Ames St (in front of Greenway Center);
  • Complete west-side sidewalk reconstruction at the SW corner of the bridge;
  • Begin east-side sidewalk reconstruction b/t Blaine St. & Benning Rd.;
    • During sidewalk reconstruction, pedestrians will be diverted to temporary protected walkways in the new roadway (on the same side of the street).
  • Continue east-side bioretention cell/LID structure footing installations b/t Blaine St. & Benning Rd.;
  • Begin reconstruction of east-side property walls b/t Blaine St. & Clay Pl.;

> February 4: Project Photos

> February 4: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, February 4 – Friday, February 10, 2017
(Work is scheduled for Saturday, February 4, 2017)

All work subject to change (weather permitting)

  • Complete streetlight conduit installation @ the west side of the Minn. Ave & A St. intersection;
  •  Abandon old fire hydrant at the NW corner of Minn. Ave. & A St.;
  • Complete sidewalk reconstruction @ the west side of Minn. Ave. bridge over East Capitol St;
  • Continue installation of traffic signal communication cables through new manholes & ductbanks b/t Ames St. & Ridge Rd.;
  • Begin coping wall construction (back of sidewalk areas), west side  b/t A St. & Dix St;
  •  Open west-side (southbound) Ames St. bus stop, which has been relocated to south of Ames St (in front of Greenway Center);
  • Begin property wall and bioretention cell/LID structure footing installations, east side of Minn. Ave. b/t Benning Rd. & Blaine St.;
  • Begin sidewalk reconstruction, east side of Minn. Ave. b/t Benning Rd. & Blaine St.;
    • During sidewalk reconstruction, pedestrians will be diverted to temporary protected walkways in the new roadway (on the same side of the street).