Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, April 29 – Friday, May 5, 2017
(Work is scheduled on Saturday, April 29th, 2017)

All work subject to change (weather permitting)

**Project is nearing completion with roadway paving to begin this week concurrent with continued landscaping and traffic signal/lighting work. 

Expected project completion is July 1st, 2017.

  • Continue construction of new roadway medians b/t A St. & Blaine St.;
  • Continue construction of new brick steps, east side b/t Ames St. & Blaine St.;
  • Continue construction of brick wall @ the SE corner of Minn. Ave. & Ridge Rd.;
  • Continue installation of new streetlight, traffic signal poles and power/communications cables project-wide;
  • Continue placement/construction of LID/bioretention cell (tree and planter box) bedding materials (pipe and aggregates) and begin adding planting soils;
  • Abandon existing 8” water main, west side in front of Subway/DLTR;
    • The abandonment of this main will require a night water shutdown.  Advance notice will be provided by DC Water.
  • Begin roadway milling and paving operations project wide;
    • **In order to avoid major traffic disruptions, work will occur during the evening and overnight hours, starting after 7 PM and continuing through the overnight hours. Please see DDOT and/or Project website for Advisory/additional information.   

> April 22: Project Photos

> April 22: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, April 22 – Friday, April 28, 2017
(Work is NOT scheduled on Saturday, April 22nd, 2017)

All work subject to change (weather permitting)

  • Continue construction of brick wall/copings @ the SE corner of Minn. Ave. & Ridge Rd.;
  • Continue installation of new streetlight, traffic signal poles and communications cables project-wide;
  • Continue construction of new roadway median b/t A St. & Ridge Rd.;
  • Abandon existing 8” water main, west side in front of Subway/DLTR.
    • The abandonment of this main will require a night water shutdown.  Advance notice will be provided by DC Water.
  • Begin installation of planting/bioretention soils @ planter boxes project-wide.

> April 15: Project Photos

> April 15: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, April 15 – Friday, April 21, 2017

(Work is NOT scheduled on Saturday, April 15th, 2017 but is scheduled on DC Emancipation Day, Monday, April 17th, 2017)

All work subject to change (weather permitting)