> August: Weekly Reports

During this reporting period (week ending August 25th, 2017), work included old streetlight (SL) removals, stormdrain (SD) structure cleaning, completion of final inspections and the start of addressing punch list work. To date work is approximately 98.00% complete. New TSs @ 4 intersections are fully operational, all new SLs are energized and all traffic lanes are open. Remaining work includes the installation of a new fence @ the bridge over East Capitol St., the completion of bioretention cell & tree well fence installations (currently about 85% complete) and punch list repairs/finishing touches as a result of final inspections. Expected completion date excluding punch list work is August 31st, 2017.