> April 29: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, April 30 – Friday, May 6, 2016
(Work is scheduled for Saturday, April 30, 2016)

All work subject to change (weather permitting).

  • Workzone continues in Minn. Ave. northbound lanes & at Ridge Rd., e. of Minn. Ave.:
    • Continue new roadway reconstruction b/t A St. & Dix St.;
    • Continue reconstruction of Ridge Rd., east of Minn. Ave., including subgrade preparation, underdrain, wheelchair ramp, curb & gutter installations and utility manhole adjustments;
    • Continue curb/gutter, wheelchair ramp & bus pad installations b/t A St. & Dix St.;
    • Continue stormdrain pipe & inlet installations b/t Dix St. & Benning Rd.;
    • Continue streetlight/traffic signal MH/conduit installation b/t A St. & Benning Rd.;
    • Continue streetlight pole foundation installations b/t Clay Pl. and Dix St.;
    • Continue demolition of Minn. Ave. northbound lanes b/t Dix St. & Benning Rd.;
    • Continue demolition and reconstruction of eastbound side of Dix St. @ Minn. Ave.

** Note:  Dix St. will temporarily become one way westbound @ Minn. Ave. through the first half of the week until it can be repaved and reopened.  Traffic will be detoured to Clay Pl.


> April 22: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, April 23 – Friday, April 29, 2016
(Work is scheduled for Saturday, April 23, 2016)

All work subject to change (weather permitting).

  • Workzone will continue in Minn. Ave. NB lanes (e. side) & at Ridge Rd., e. of Minn. Ave.:
    • Continue new roadway reconstruction b/t A St. & Dix St.;
    • Continue reconstruction of Ridge Rd., east of Minn. Ave., including subgrade preparation and underdrain  pipe installation;
    • Continue curb/gutter, wheelchair ramp & bus pad installations b/t A St. & Dix St.;
    • Continue stormdrain pipe & inlet installations b/t Dix St. & Benning Rd.;
    • Continue streetlight/traffic signal MH/conduit installation b/t A St. & Benning Rd.;
    • Continue streetlight pole foundation installations b/t Blaine St. & Clay Pl.;
    • Continue demolition of Minn. Ave. NB lanes b/t Dix St. & Benning Rd.;
    • Begin demolition and reconstruction of EB side of Dix St. @ Minn. Ave.

** Note:  Access to East Capitol St. from SB Minn. Ave. and from East Capitol St. to Minn. Ave. (at Ames St.) will be restored Monday morning, 4/25/16


> April 15: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, April 16 – Friday, April 22, 2016
(Work is scheduled for Saturday, April 16, 2016)

All work subject to change (weather permitting).

  • Continue roadway reconstruction of Minn. Ave. NB lanes b/t A St. & Dix St., including installation of new roadway pavement (subsurface) sections b/t Ames St. & Dix St.;
  • Continue roadway subgrade and underdrain pipe installation b/t A St. &  Ridge Rd.;
  • Continue curb/gutter and wheelchair ramp installations b/t A St. & Dix St.;
  • Continue roadway demo & reconstruction of Ridge Rd., east of Minn. Ave.;
  • Continue stormdrain pipe & inlet installations @ Ridge Rd., east of Minn. Ave.;
  • Continue streetlight/traffic signal manhole/conduit installation b/t A St. & Benning Rd.;
  • Continue streetlight pole foundation installations b/t Blaine St. & Clay Pl.;
  • Begin demolition of Minn. Ave. NB lanes b/t Dix St. & Benning Rd.

> April 8: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, April 9 – Friday, April 15, 2016
(Work is scheduled for Saturday, April 9, 2016)

All work subject to change (weather permitting).

  • Continue roadway demo & reconstruction of Minn. Ave. NB lanes b/t A St. & Dix St.;
  • Begin roadway demo & reconstruction of Ridge Rd., east of Minn. Ave.;
  • Begin constructing roadway pavement section (4" drainable base course bottom layer) b/t Ames St. & Blaine St.;
  • Continue demolition/reconstruction @ the NE corner of Minn. Ave. & Clay Pl. (east side);
  • Begin roadway demolition/reconstruction @ the SE corner of Minn. Ave. & Dix St. (Dix St. will temporarily become 1 way westbound @ Minnesota Ave.);
  • Continue roadway subgrade and underdrain pipe installation b/t Blaine St. & Dix St.;
  • Continue stormdrain manhole, pipe & inlet installations b/t A St. & Benning Rd.
  • Continue streetlight/traffic signal manhole/conduit installation b/t A St. & Benning Rd.
  • Continue curb/gutter, wheelchair ramp and driveway installations b/t E. Capitol St. Bridge & Dix St;
  • Continue streetlight pole foundation installations b/t Ames St. & Clay Pl.

> April 1: Project Updates

Minnesota Avenue Revitalization Phase 1
from A St., SE to 300 ft. south of Benning Rd., NE

PROJECT UPDATE

Saturday, April 2 – Friday, April 8, 2016
(Work is scheduled for Saturday, April 2, 2016)

All work subject to change (weather permitting).

  • Continue roadway demolition/reconstruction including curb & gutter b/t A St. & Dix St.;
  • Continue demolition/reconstruction @ the NE corner of Minn. Ave. & Clay Pl. (east side);
  • Begin roadway demolition/reconstruction @ the SE corner of Minn. Ave. & Dix St. (Dix St. will temporarily become 1 way westbound @ Minn. Ave.);
  • Continue roadway subgrade and underdrain pipe installation b/t Blaine St. & Dix St.;
  • Continue stormdrain manhole, pipe & inlet installations b/t A St. & Benning Rd.;
  • Continue streetlight/traffic signal manhole/conduit installation b/t A St. & Benning Rd.;
  • Continue curb/gutter & wheelchair ramp installations b/t E. Capitol St. Bridge & Dix St.;
  • Continue streetlight pole foundation installations b/t Ames St. & Clay Pl.